Steps to Create BPA Projections
The following are the steps to create BPA Projections.
Update Entities Profile
- Go to BPA>Profiles>Entities
- Select and edit required profile
- Click on the Entities grid and select
- Filter the selection prompt for the following:
- Date Placed 'does not equal' 11/30/1899
- GRN=H
- Status=Active
- Farm Stage=Lay
- Click OK
- Save and close entity screens
Update Entity History
- Go to BPA>Planning>Entity
History
- Highlight all entities
- Select Options>Import
Weekly Data for existing entities or Select Options>Import All
Data for new entities
- Review entities for
accuracy. Any adjustments can be made on the Adjustments tab.
- If POL Date is not
defined, enter the required POL date.
- Highlight all entities
and select 'Calculate'.
Update Movements
- Go to BPA>Planning>Movements
- Verify that the following fields match the entities
that were imported to Entity History:
- Complex Entity No
- Date Placed
- Breed
Calculate Projection
- Go to BPA>Projections>Entity
Performance
- Highlight the profile and select 'Calculate'
- When complete, right-click on profile and select
desired view to review the data